Dalby Gas Pipeline Realignment EPC Project
Location

Dalby, QLD

Client

United Petroleum

Duration

6 Months

Type

Brownfields EPC

Case Study
Dalby Gas Pipeline Realignment EPC Project


Scope

Realignment of the Dalby Gas Pipeline (DGP) due to the Warrego Highway upgrade. Includes engineering design, procurement, construction and commissioning of new section and decommissioning of old section.


Key Achievements

  • Detailed design of new section, procurement of new line pipe and associated facilities and equipment.
  • Construction approvals, planning, risk assessment, stakeholder engagement and community consultation.
  • Management of out of service activities for tie in including blow down, out of service purge and re-introduction of gas.
  • On site construction management including productivity, safety and quality management of trenching, welding, lowering in, backfilling and reinstatement activities.